Site preparation for a new house in Spartanburg or Greenville County runs in a set order: survey, permits, a utility locate through SC811, clearing, erosion control, the house pad and the access drive. Each step depends on the one before it, and getting the order wrong is what costs time.
1. Survey and lot layout
Start with the boundary. Have the lot surveyed and the corners marked before any tree comes down. Clearing past your line is an expensive mistake that cannot be undone.
Then place the house on paper. Setbacks, easements, any flood zone and the route of the drive all come into it. Your builder, designer or engineer usually draws this up as a site plan.
Walk the lot with that plan in hand. Look at where water runs after a rain, where the high and low spots are and where a truck can come in. Most site prep questions are answered on that walk. It is also when we would like to see the ground, before the plan is final.
2. Permits: county or city
Who issues your permits depends on where the lot is. In unincorporated Spartanburg County, applications go through the county's Citizen Self Service portal, where Planning, Engineering and Building Codes reviews can run together. The county also has its own land disturbance permit application, including one for sites under an acre.
In unincorporated Greenville County, building permits go through Building Safety. The county's Land Development Division reviews plans for stormwater before a grading permit is issued.
Inside city limits, such as Spartanburg, Greenville or Greer, the city's own planning and building office may handle it. Call the office for your parcel and confirm what you need before work starts.
3. SC811 and private lines
South Carolina law requires a locate request through SC811 before any excavation. Utility owners then mark their lines. There is a waiting period before digging can start, so build it into the schedule.
SC811 members only mark the lines they own. Private lines are not marked by them. That includes wells, irrigation, power run to a barn or shop and any line the owner put in. SC811 points owners to private locating companies for those. If you know where a private line runs, mark it and tell your contractor before the machine arrives.
On raw land there may be nothing underground at all. The locate is still the step that proves it.
4. Clearing and erosion control
Clear only what the plan needs. The house, the drive, the work area and the utility routes have to be opened up. Stumps and roots come out wherever something will be built. The rest of the lot can often be mulched or left alone. See land clearing.
Bare red clay washes fast. Silt fence, stone entrances and other controls keep mud on the lot and out of the street and streams.
Bigger projects carry state rules. SC DES requires coverage under its construction stormwater general permit, with a Stormwater Pollution Prevention Plan (SWPPP) and a Notice of Intent, when a project disturbs an acre or more or is part of a larger common plan. A lot in a subdivision can fall under that. Ask the county which applies to yours.
5. House pad and access drive
Topsoil is stripped from the building area and saved for the yard. Then the pad is cut and filled to the height on the plans. Fill goes in thin layers, each compacted before the next. The pad is shaped so water runs away from it. Our house pad guide covers this step in detail.
The access drive goes in early, not last. A loaded concrete truck has to reach the footers, and wet clay will not carry one. A stone base laid now can be topped with finish stone after the heavy trucks are gone.
Drainage is shaped at the same time. Ditches above the pad and a culvert where the drive crosses a low spot cost less to put in now than after the house is up.
6. Utilities and the hand-off to the builder
Water, sewer, power and gas lines are usually trenched by the plumber, the electrician or the utility provider, on their own schedule. Leave a clear route for them on the site plan so the pad and drive do not block it.
When the site work is done, the builder should get a firm pad at the right height, an access drive that holds a loaded truck, water moving away from the house and erosion controls in place.
M&S Land Management does the clearing, grading, pad, drive and drainage as one crew across the Upstate. See site preparation in Spartanburg, call (828) 540-6856 or ask for a free estimate.
The Short Version
- Survey the boundary and draw a site plan before anything is cleared.
- Confirm permits with the county or city office for your parcel. Spartanburg and Greenville counties each run their own review.
- Submit an SC811 locate before digging. Private lines are the owner's to have marked.
- Projects disturbing an acre or more, or part of a larger plan, need SC DES stormwater coverage and a SWPPP.
- Pad and access drive come before the footers. Utility trenches follow on the trades' schedule.
Quick Answers
What should I look for in site preparation contractors near me?
Look for one crew that can clear, grade, build the pad, put in the access drive and handle the drainage. Ask what is included, how they handle wet clay and whether they will walk the lot before giving a price. M&S works across Spartanburg and Greenville counties. Call (828) 540-6856.
Do I need a permit to clear and grade my lot in the Upstate?
It depends on the parcel and how much ground is disturbed. Spartanburg County has its own land disturbance permit, Greenville County reviews stormwater through its Land Development Division, and SC DES covers projects of an acre or more. Call the county or city office for your parcel before you start.
Who marks private water and power lines before digging?
SC811 members only mark the lines they own. Private lines, such as a well line or power to a shop, are the owner's to have marked. SC811 lists private locating companies for that.
Should the driveway go in before the house is built?
Yes, at least the base. Concrete and material trucks need a firm route to the pad. Finish stone can go on after the heavy trucks are done.